Line Extension &
Electric Switchover Policy
Extension of Service
The City of Austin generally does not
charge the customer for the normal extension of service. A
customer may be required to make a Contribution in Aid of
Construction for the extension of service if the current source
is more than 300 feet from the point of delivery. Any required
contribution will not include costs for facilities that are
normally provided by the City of Austin, such as transformers,
meters, and service drops.
The distance is measured along the route
of the new line from an existing source to the point of delivery.
The customer will be required to pay for all costs not normally
provided for by the City of Austin less a share of revenues
described below.
If more than one customer is requesting
service from the same extension, the length of service extended
without a fee is equal to the product of (1) the number of
customers to be served from the line, and (2) 300 feet.
The required contribution for an extension
beyond 300 feet will be the difference between (1) the excess
costs for the extension, and (2) 20% of the estimated base
revenues collected from the new customer over a three year
period
Customer Switchover
In a dually certified service area,
a customer is required to pay all current balances before
being disconnected from the City of Austin Electric system.
The customer will also be required to pay, in advance, for
any costs associated with the disconnection of service. There
will not be a disconnect fee in addition to the above costs.
A customer switching to the City of Austin
Electric system from another system will be required to present
a receipt or other evidence from the disconnecting utility
that all current charges for electric service and for the
service disconnection have been paid.
We make every effort to be accurate in
displaying rates online. In case of conflict, the official
tariffs on file with the City Clerk's office take precedence.
|